Active Alerts

If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or (415) 701-2311 from outside SF or log on at sf311.org. Learn more or review active service alerts.

Hampshire and York Streets Utility Upgrade Project

Overview

Critical upgrades to our aging water and sewer infrastructure are planned for:

  • Hampshire and York streets between Mariposa and Cesar Chavez streets
  • Bryant Street between Precita Avenue and 26th Street
  • 23rd and 25th streets between Hampshire Street and Potrero Avenue
  • 26th Street between Bryant and Hampshire streets
  • Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp 

This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration. 

Construction Look Ahead

  • Week of April 8th
    Excavation and installation of water main - York Street between 18th and 21st streets
    Curb ramp upgrades - Intersection of 19th and York streets; Intersection of 20th and York streets
     
  • Week of April 15th
    Excavation and installation of water main - York Street between 18th and 20th streets 
    Curb ramp upgrades - Intersection of 19th and York streets; Intersection of 20th and York streets
     
  • Week of April 22nd
    Curb ramp upgrades - Intersection of 21st and York streets
     

Check out our What to Expect During Construction fact sheet for a helpful overview. 

Map showing where construction will take place for the Hampshire and York streets project

  • Construction Start: July 2023
  • Construction End: December 2025
  • Project Phase: Construction