Active Alerts

If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or (415) 701-2311 from outside SF or log on at sf311.org. Learn more or review active service alerts.

Pine Lake Park Slope Restoration Project

Overview

NOTE: The Vale Parking lot and Pine Lake Park dog meadow are open but may experience temporary closures when equipment is being brought in or out of the park.


April 2024 Update:

To improve ADA access on the paved trail south of the dog park, our crews will be removing three speed bumps during the week of April 15th. There will be jackhammering, dust and noise during the demolition.

Our engineers have taken soil samples for testing and have begun to develop a slope stabilization design. This design will take into account how best to support existing infrastructure at that location including both the water transmission line and a sewer main. Reconstruction work on the slope will begin once a formal design has been reviewed and approved.


On March 8, 2024, an 8-inch air valve connected to a 60-inch water transmission line failed, just below the end of the 1700 block of Wawona Street, above the Pine Lake Park dog park.  

That transmission line feeds water from our treatment plant on the San Francisco Peninsula to the Sunset Reservoir, which is one of the largest serving the residents of the city.

Water streaming from the air valve caused a geyser above the area which then flowed down a steep slope into the park, scouring a path to the park below until the crews onsite were able to shut the leak down.

The week of March 11, 2024 the SFPUC identified a construction contractor and an engineering consultant who will work with the agency to determine a scope and schedule for repairs, including the hillside and the dog park area.

Map is approximate and not to scale.  Blue area is the location of the impacted slope. Yellow area is the debris field.

image shows area of slope below the 1700 block of Wawona Street impacted by the water

The first phase of work to prepare for restoration of the area was to remove hazardous trees.  That included all trees that became dangerously undermined by the scouring action of the water.  This work began on March 11th and was completed on March 21st.

Photo showing crews cutting up fallen trees

The second phase of work involved covering the affected area of the slop with plastic sheeting to prevent further erosion. That work was completed on March 22nd.

Image of Pine Lake Park slope covered with white plastic sheeting

  • Construction Start: March 2024
  • Construction End: Fall 2024
  • Project Phase: Design